Alignment Summary

To view a summary of the construction quantities and costs for the selected alignment, click on the Alignment Summary in the Report tab. 

The Alignment Summary dialog appears.

To report the costs and quantities with higher accuracy, change the significant figures in the Preference Settings dialog. See Appendix D.

The Alignment Review Summary window gives the alignment name and total cost at the top, then a detailed breakdown of construction parameters and costs that contribute to the overall cost. Generally, the window has quantities and costs divided into five main categories:

At the bottom of the Alignment Review summary window is a button and report on the number of Warnings present in the loaded alignment. Many of the items within the Alignment Review summary window are highlighted with a blue hyperlink. This hyperlink can be used to open a corresponding dialog box providing more detailed information on a given item. For more details, click any item that is underlined and a report window will open.

The areas and costs are summed over all zones of a given type.

The Footprint Area shown in the Area cost summary dialog is the area underneath the earthworks (when earthworks exist) plus the area of the pavement when the alignment is on a bridge or in a tunnel, plus the area of any margin. Because area cost zones can overlap and a margin is included when calculating the areas, the sum of the areas in the Area cost summary can exceed the area shown in the Alignment Review Summary.

Multiple encounters with a single zone will produce multiple entries.

To see the type, start, finish, and severity of any warnings, in the Alignment Review Summary dialog, click : (icon)

Variations

The variations include:

Curves

Straights

Grades

Intrusion into avoid zones

Missing the vertical window when crossing a feature or zone

Low grades (<0.2%) below ground

Distance between culverts in a culvert zone too great